One thing I’ve discovered in working with clients is they often have little idea what architects actually do behind the scenes before a design presentation or even in the process of creating the documents necessary for pricing and constructing a building. They may have some idea, such as that drawing is somehow involved, perhaps the use of CADD, and that an architect needs some balance of abilities hovering between art, engineering, and science. They would be shocked to know that, while in general terms these aspects may be accurate, the reality of practice today has a lot to do with other skills and priorities. This post will be the first in a series covering what really goes on inside the “black box” of Synchronis. While I will not say this is typical of most architectural practices, it is my story of how Synchronis addresses the myriad requirements we face as an ongoing practice, along with the opportunities for advancing the practice into the future.
There is a famous quote attributed to Picasso, who had doodled on a napkin in a Parisian sidewalk cafe. A passerby asked if he might buy the napkin sketch, to which the artist requested something like $1M Francs. The passerby complained it took only five minutes to create the sketch, to which Picasso replied something to the extent of, “Non monsieur, it took a lifetime for me to create this sketch in five minutes.” To be clear, I’m no Picasso, but what’s become relatively quick and easy for me now has a few decades of experience behind it in order to do what I do efficiently and well.
For this story, I will use a fun and fast conceptual study we did a few years ago for a “puzzle piece” shaped urban infill site in Los Angeles Chinatown.
Step 1: Obtaining the Client’s Project Definition
Our commercial developer client asked me to test the maximum density of parking, retail space, and residential apartment units which could be constructed on a site that was available for purchase. This was conceived as a relatively large, 380 residential unit concrete high-rise project with an estimated construction cost of $130M. This design approach for a commercial project is not representative of how we work on a school, a church, or a wood single-family house. Those clients have unique requirements for collaboration and communication and we adjust our methods accordingly. In this assignment for a mixed-use project, the client asked me to maximize the number of apartment units allowed by the jurisdiction, Because the site spanned a city block and faced two busy throughfares, the client wanted to include a street-facing “big box” retail space of at least 60,000 square feet suitable for a single, large convenience store tenant. This is often the extent of what could be called a program for a commercial project as the mix is established as a wish list of sorts which may be vetted during the development of the concept plan and checked against a fluid financial model or proforma which establishes whether the project actually pencils-out and will viably attract investors and bank lenders.
Developers are challenged by the economics of ever-rising construction costs, maintaining the affordability and competitiveness of rents, the cost of borrowing money, and a extracting a reasonable profit to make the risk of developing a project worthwhile. Hence, there are some economies in the implementation of floor plans and the stacking of units which any experienced multifamily building architect will know well. While there is no practical limit to how complex and interesting a design may be conceived, the marketplace realities set limits to the complexity based on the need to deliver a commercially viable product.
Step 2: Understanding the Design Limitations Set by the Jurisdiction
While architects may differ in where this step falls in the sequence of events. I like to place this one first after receiving the client’s project definition as it makes the subset of problems to be addressed in the latter phases fewer and thus less daunting. One might think a blank slate is ideal, however when time and costs are limited, I find constraints are actually a good thing when implementing something as pragmatic as a commercial building product. The first step here is to obtain an accurate site plan and property line boundary and quickly develop an inventory of the applicable zoning requirements. These include establishing so called setbacks or no-build zones inboard of the property lines. Most cities establish large front and back yards and relatively narrow side yards if the site is in a suburban area. For urban infill sites such as this one, so called zero setbacks are often allowed such that buildings front directly on a sidewalk and directly adjacent to their neighboring buildings. The latter with the proviso that adequate space for earthquake movements must be allowed for so that buildings do not damage each other when the shaking starts. The building code, which is a lengthy set of technical stipulations a jurisdiction has adopted to maximize occupant life safety, will set limitations on the size and fire rating of windows based on their proximity to property lines, so these requirements are factored-in as well in the development of the floor plans.
The other zoning requirements are typically default allowances for site coverage by the building footprint, a minimum size for residential units (if applicable), the maximum height of the building, and any accommodations for increased building density based on bonuses such as proximity to public transit, incorporation of affordable units, or an assumption by the developer that a project-specific zoning will be obtained based on obtaining a so-called Conditional Use Permit.
Step 3: Determining the Building Structure
While this step might be the result of evaluating several options, in an urban infill site with a goal to achieve a maximal buildout, either so-called Type I or Type II incombustible construction is the go-to choice. When required to be incombustible, the materials to be used are uniformly steel, concrete, masonry, or some combination of these three structural materials. One often sees apartment buildings in suburban sites or urban sites where building heights are capped and up to six stories combustible wood construction are constructed over a podium of one or two-levels of concrete construction. This is done to minimize the constructed cost, albeit at some sacrifice of overall life-cycle costs. In this example, a so-called prestressed, flat slab concrete structural system was assumed in order to minimize the floor-to-floor heights and maximize the number of building stories that could be built under the building height limitations established by the site zoning. As an aside, steel buildings will typically require approximately three to four feet of additional vertical height per story, thus effectively reducing the number of buildable stories (where building heights are limited) by 30% to 40% if used. At Synchronis, we have not yet had the opportunity to implement mass timber, a optimally sustainable structural material choice, but its use of glue-laminated beams as opposed to a flat slab, and the overall costs make these somewhat similar in application to the use of steel.
Step 4: Designing for Stuff at the Bottom, i.e., Cars, Trucks, Lobbies, and Street-fronting Retail


Having established the site boundaries and the zoning requirements, the next step, for me, is not yet to get out a sketchbook and dream about the beautiful building to be. The commercial realities for a viable retail project and a marketable apartment building is that LA people have cars. The next step is to figure out ingress and egress for cars and delivery trucks, where the building lobbies, elevators and escalators would be situated, how many cars can be accommodated per parking level, and some idea where the building mechanical, electrical, and fire life-safety systems will be accommodated.
In studying the above, I first looked at a balance of below-grade and above grade parking to accommodate more cars but finally arrived at 100% above grade parking to limit the overall project cost. Below-grade parking runs at least three times the cost per car as above-grade parking. Having opted for a concrete structural system, a grid of concrete columns allowing for drive aisles and parking spaces between them is established which carry through both the below-grade and above-grade parking levels. At this point in the process we are using Revit, an industry-standard Building Information Modelling (BIM) software platform, which models the design in 3D. Synchronis no longer uses CADD to manually draft, but instead extracts 2D drawings from a 3D virtual building which is initially constructed in these early phases of conceptual study and constantly refined in the latter design stages.

Step 5: Designing the Dwelling Units
In a feasibility study such as this one where the property is not yet purchased, I establish the number of units based on multiples of a design module of a specific width and depth. I found this method works well for designing apartments that are shallow enough in depth that daylight and view can still reach the unit’s entry door and to allow the living area and bedrooms to all have direct access to exterior windows. Corridors are double-loaded wherever possible to maximize the ratio of rentable area to non-rentable circulation space. In this case, I opted to make these corridors open-air breezeways (a further bonus of using a weather-resistant structural material like concrete) to both enhance the garden-like atmosphere on a floor, as well as to reduce the cost of providing interior finish materials and conditioned air. A studio apartment was allocated as either 1 or 1.5 design modules in size, a 1-bedroom apartment as two design modules, and a 2-bedroom apartment as three modules in size. Because of this use of design modules, it was not necessary to finalize the design of the unit layouts at this stage and the mix of units can be easily adjusted at any point.
Designing for High-Rise

For high-rise buildings, one has to have a sense about what sorts of infrastructure accommodations need to be made in the lower building levels. In this case parking spaces needed to be deducted to roughly accommodate a large fire water storage tank, a vault for electrical equipment servicing the building, an emergency generator, and so on.
In this particular study, because of the irregular property line boundaries, the parking level floor plans did not lend themselves to the use of sloped parking floors in lieu of ramps so establishing the location of a dedicated speed ramp as well as truck loading areas for the street level retail created a unique challenge.
At this point, you may already be surprised that so much technical knowledge and effort is applied to produce some floor plan sketches and a “pretty” rendering. The required effort has to do with the commitment to be made as to how much rentable area will be available at the end of the day as well as an idea of overall project cost. Without reasonably accurate data on these two things, an owner or developer will not be able to establish the viability of purchasing a property and know at what price to make a purchase offer.
Client Reviews and Feedback
While Steps 1 through 5 are occurring, we are regularly sending progress images to our client, holding in-person or Zoom meetings and adjusting the assumptions as we go. We are also starting to get our outside professional renderer clued-in so that they will be ready to start the creation of a final rendering image based on the development of Step 6, to follow.
Step 6: Designing the Architecture
For me, all the above steps lead to the creation of an optimal diagram, the conceptual core of the building design which I know will function well. Once that is worked-out and adjusted to a satisfactory level, the architect (me) finally gets to practice what everyone outside the black box thinks is what we do all the time. A pure diagram will generally look rather oppressive and repetitive. I often joke that all my designs start off looking like a stereotypical psychiatric hospital. With this knowledge, I no longer worry too much about how things look initially upon the completion of the optimal diagram. Because we have constructed this armature of a building design on a computer in 3d. I usually don VR goggles at this point and start critiquing the forms and thinking about how I might manipulate the massing, select materials, and so on. In actual fact, I will often harbor some idea or strategy about this final intention while Steps 1 through 5 are occurring so that Step 6 is a little less formidable. In this case, I was thinking about deliberately celebrating the “puzzle piece” nature of the site by emphasizing the jogs, pulling elements forward and back from the edge of the footprint and liberally switching the wall materials between brick veneer, metal panel, and raw cast concrete. After a number back and forth revisions with my team, my critiquing the progress through VR, and my sketching in digital pen over screenshots, we have an initial design that is I feel is worthy of presenting to our client. The look is intentionally a little tough and urban industrial-chic, in keeping with the Chinatown context. Additional architectural revisions are made based on client feedback over the next week. Voila, we now have a concept design for a $130M mixed use project along with accompanying spreadsheets tabulating square footages and budget costs. Time from start to completion: six weeks. Incidentally, we also proposed a way the client could opt to reduce approximately $20M of the construction cost using what we called Predictive Workflow™ design and the implementation of prefabricated, plug-in cassettes for the residential units. We have subsequently developed the Inhabio system precisely for this purpose and have been rolling this out on four client projects in 2025.